{"id":9227,"date":"2023-09-01T09:22:06","date_gmt":"2023-09-01T07:22:06","guid":{"rendered":"https:\/\/kjellfoss.no\/?p=9227"},"modified":"2025-11-05T12:30:53","modified_gmt":"2025-11-05T11:30:53","slug":"e134-arhus-seljord","status":"publish","type":"post","link":"https:\/\/kjellfoss.no\/en\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/","title":{"rendered":"E134 \u00c5rhus in Seljord"},"content":{"rendered":"<p>Ny veilinje E134. Sprengning av skj\u00e6ring\/veilinje. 67000m3 veiskj\u00e6ring med kontursprengning p\u00e5 begge sider av skj\u00e6ringen direkte under h\u00f8yspent.\u00a0<\/p>\n\n\n\n<div class=\"wp-block-gmap-gmap-block gmap-block-udjdb2dp\"><iframe src=\"https:\/\/maps.google.com\/maps?q=e134&amp;z=11&amp;t=roadmap&amp;output=embed\" class=\"embd-map\" title=\"e134\"><\/iframe><\/div>\n\n\n\n<figure class=\"wp-block-gallery has-nested-images columns-default is-cropped wp-block-gallery-1 is-layout-flex wp-block-gallery-is-layout-flex\">\n<figure class=\"wp-block-image size-large\"><img fetchpriority=\"high\" decoding=\"async\" width=\"1024\" height=\"786\" data-id=\"10910\" src=\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/3.jpg-Seljord2-1024x786.jpg\" alt=\"Kjell Foss utf\u00f8rte kontursprengning av 165 000 m\u00b3 for veiskj\u00e6ringer p\u00e5 E134 \u00c5rhus \u2013 Seljord, ferdigstilt i 2022.\" class=\"wp-image-10910\" srcset=\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/3.jpg-Seljord2-1024x786.jpg 1024w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/3.jpg-Seljord2-300x230.jpg 300w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/3.jpg-Seljord2-768x590.jpg 768w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/3.jpg-Seljord2-16x12.jpg 16w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/3.jpg-Seljord2.jpg 1250w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" width=\"1024\" height=\"786\" data-id=\"10909\" src=\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/6.jpg-Seljord-1024x786.jpg\" alt=\"Kontursprengning p\u00e5 begge sider av skj\u00e6ringen p\u00e5 E134 \u00c5rhus \u2013 Seljord. Ferdigstilling i 2022 med h\u00f8y presisjon og kvalitet.\" class=\"wp-image-10909\" srcset=\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/6.jpg-Seljord-1024x786.jpg 1024w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/6.jpg-Seljord-300x230.jpg 300w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/6.jpg-Seljord-768x590.jpg 768w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/6.jpg-Seljord-16x12.jpg 16w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/6.jpg-Seljord.jpg 1250w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" width=\"1024\" height=\"786\" data-id=\"10911\" src=\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/7.jpg-Seljord-3-1024x786.jpg\" alt=\"165 000 m\u00b3 fjell sprengt med kontursprengning p\u00e5 E134 mellom \u00c5rhus og Seljord. Effektive l\u00f8sninger levert av Kjell Foss.\" class=\"wp-image-10911\" srcset=\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/7.jpg-Seljord-3-1024x786.jpg 1024w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/7.jpg-Seljord-3-300x230.jpg 300w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/7.jpg-Seljord-3-768x590.jpg 768w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/7.jpg-Seljord-3-16x12.jpg 16w, https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/09\/7.jpg-Seljord-3.jpg 1250w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n<\/figure>\n\n\n\n<p><\/p>","protected":false},"excerpt":{"rendered":"<p>Blasting of rock cut\/road alignment using contour blasting.<\/p>","protected":false},"author":1,"featured_media":9235,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[20,3,22],"tags":[35],"class_list":["post-9227","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-ferdig","category-tidligere-prosjekter","category-vei-og-jernbaneprosjekt","tag-anders-saetre-torp"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.1.1 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>E134 \u00c5rhus \u2013 Seljord | Veiskj\u00e6ringer med kontursprengning<\/title>\n<meta name=\"description\" content=\"Kontursprengning av 165 000 m\u00b3 fjell for veiskj\u00e6ringer p\u00e5 E134 \u00c5rhus \u2013 Seljord. Effektive og presise sprengningsl\u00f8sninger.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/kjellfoss.no\/en\/previous-projects\/road-and-railway-project\/e134-arhus-seljord\/\" \/>\n<meta property=\"og:locale\" content=\"en_GB\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"E134 \u00c5rhus \u2013 Seljord | Veiskj\u00e6ringer med kontursprengning\" \/>\n<meta property=\"og:description\" content=\"Kontursprengning av 165 000 m\u00b3 fjell for veiskj\u00e6ringer p\u00e5 E134 \u00c5rhus \u2013 Seljord. Effektive og presise sprengningsl\u00f8sninger.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/kjellfoss.no\/en\/previous-projects\/road-and-railway-project\/e134-arhus-seljord\/\" \/>\n<meta property=\"og:site_name\" content=\"Kjell Foss AS\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/kjellfoss.no\/\" \/>\n<meta property=\"article:published_time\" content=\"2023-09-01T07:22:06+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2025-11-05T11:30:53+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/08\/6.jpg-Seljord.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1250\" \/>\n\t<meta property=\"og:image:height\" content=\"960\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Ida Christine\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Ida Christine\" \/>\n\t<meta name=\"twitter:label2\" content=\"Estimated reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"1 minute\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#article\",\"isPartOf\":{\"@id\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/\"},\"author\":{\"name\":\"Ida Christine\",\"@id\":\"https:\/\/kjellfoss.no\/#\/schema\/person\/1a569ead06f21069a291154e44c08ee9\"},\"headline\":\"E134 \u00c5rhus &#8211; Seljord\",\"datePublished\":\"2023-09-01T07:22:06+00:00\",\"dateModified\":\"2025-11-05T11:30:53+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/\"},\"wordCount\":27,\"publisher\":{\"@id\":\"https:\/\/kjellfoss.no\/#organization\"},\"image\":{\"@id\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/08\/6.jpg-Seljord.jpg\",\"keywords\":[\"Anders S\u00e6tre Torp\"],\"articleSection\":[\"Ferdig\",\"Tidligere prosjekter\",\"Vei og jernbaneprosjekt\"],\"inLanguage\":\"en-GB\"},{\"@type\":\"WebPage\",\"@id\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/\",\"url\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/\",\"name\":\"E134 \u00c5rhus \u2013 Seljord | Veiskj\u00e6ringer med kontursprengning\",\"isPartOf\":{\"@id\":\"https:\/\/kjellfoss.no\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/08\/6.jpg-Seljord.jpg\",\"datePublished\":\"2023-09-01T07:22:06+00:00\",\"dateModified\":\"2025-11-05T11:30:53+00:00\",\"description\":\"Kontursprengning av 165 000 m\u00b3 fjell for veiskj\u00e6ringer p\u00e5 E134 \u00c5rhus \u2013 Seljord. Effektive og presise sprengningsl\u00f8sninger.\",\"breadcrumb\":{\"@id\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#breadcrumb\"},\"inLanguage\":\"en-GB\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-GB\",\"@id\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#primaryimage\",\"url\":\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/08\/6.jpg-Seljord.jpg\",\"contentUrl\":\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/08\/6.jpg-Seljord.jpg\",\"width\":1250,\"height\":960,\"caption\":\"Ferdig veiskj\u00e6ring p\u00e5 E134 mellom \u00c5rhus og Seljord med 165 000 m\u00b3 kontursprengning p\u00e5 begge sider av skj\u00e6ringen.\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Hjem\",\"item\":\"https:\/\/kjellfoss.no\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"E134 \u00c5rhus &#8211; Seljord\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/kjellfoss.no\/#website\",\"url\":\"https:\/\/kjellfoss.no\/\",\"name\":\"Kjell Foss AS\",\"description\":\"Fjellsprengning og fjellsikring i hele Norge\",\"publisher\":{\"@id\":\"https:\/\/kjellfoss.no\/#organization\"},\"alternateName\":\"Kjell Foss AS\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/kjellfoss.no\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-GB\"},{\"@type\":\"Organization\",\"@id\":\"https:\/\/kjellfoss.no\/#organization\",\"name\":\"Kjell Foss AS\",\"alternateName\":\"Kjell Foss AS\",\"url\":\"https:\/\/kjellfoss.no\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-GB\",\"@id\":\"https:\/\/kjellfoss.no\/#\/schema\/logo\/image\/\",\"url\":\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2025\/02\/kjell_foss_logo_horizontal_640px-1.png\",\"contentUrl\":\"https:\/\/kjellfoss.no\/wp-content\/uploads\/2025\/02\/kjell_foss_logo_horizontal_640px-1.png\",\"width\":640,\"height\":140,\"caption\":\"Kjell Foss AS\"},\"image\":{\"@id\":\"https:\/\/kjellfoss.no\/#\/schema\/logo\/image\/\"},\"sameAs\":[\"https:\/\/www.facebook.com\/kjellfoss.no\/\",\"https:\/\/www.instagram.com\/kjellfoss_as\/\",\"https:\/\/www.linkedin.com\/company\/kjell-foss-as\/\"]},{\"@type\":\"Person\",\"@id\":\"https:\/\/kjellfoss.no\/#\/schema\/person\/1a569ead06f21069a291154e44c08ee9\",\"name\":\"Ida Christine\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-GB\",\"@id\":\"https:\/\/kjellfoss.no\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/46bf5731d6e5f54c2b451c4f4c6756ccc3a79bfb90b2abd1e0bf3cea153cb2c8?s=96&d=mm&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/46bf5731d6e5f54c2b451c4f4c6756ccc3a79bfb90b2abd1e0bf3cea153cb2c8?s=96&d=mm&r=g\",\"caption\":\"Ida Christine\"},\"sameAs\":[\"http:\/\/kjellfoss.hornstaging.no\"],\"url\":\"https:\/\/kjellfoss.no\/en\/author\/ida-christine\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"E134 \u00c5rhus \u2013 Seljord | Road Cuts with Contour Blasting","description":"Contour blasting of 165,000 m\u00b3 of rock for road cuts on E134 \u00c5rhus \u2013 Seljord. Efficient and precise blasting solutions.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/kjellfoss.no\/en\/previous-projects\/road-and-railway-project\/e134-arhus-seljord\/","og_locale":"en_GB","og_type":"article","og_title":"E134 \u00c5rhus \u2013 Seljord | Veiskj\u00e6ringer med kontursprengning","og_description":"Kontursprengning av 165 000 m\u00b3 fjell for veiskj\u00e6ringer p\u00e5 E134 \u00c5rhus \u2013 Seljord. Effektive og presise sprengningsl\u00f8sninger.","og_url":"https:\/\/kjellfoss.no\/en\/previous-projects\/road-and-railway-project\/e134-arhus-seljord\/","og_site_name":"Kjell Foss AS","article_publisher":"https:\/\/www.facebook.com\/kjellfoss.no\/","article_published_time":"2023-09-01T07:22:06+00:00","article_modified_time":"2025-11-05T11:30:53+00:00","og_image":[{"width":1250,"height":960,"url":"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/08\/6.jpg-Seljord.jpg","type":"image\/jpeg"}],"author":"Ida Christine","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Ida Christine","Estimated reading time":"1 minute"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#article","isPartOf":{"@id":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/"},"author":{"name":"Ida Christine","@id":"https:\/\/kjellfoss.no\/#\/schema\/person\/1a569ead06f21069a291154e44c08ee9"},"headline":"E134 \u00c5rhus &#8211; Seljord","datePublished":"2023-09-01T07:22:06+00:00","dateModified":"2025-11-05T11:30:53+00:00","mainEntityOfPage":{"@id":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/"},"wordCount":27,"publisher":{"@id":"https:\/\/kjellfoss.no\/#organization"},"image":{"@id":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#primaryimage"},"thumbnailUrl":"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/08\/6.jpg-Seljord.jpg","keywords":["Anders S\u00e6tre Torp"],"articleSection":["Ferdig","Tidligere prosjekter","Vei og jernbaneprosjekt"],"inLanguage":"en-GB"},{"@type":"WebPage","@id":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/","url":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/","name":"E134 \u00c5rhus \u2013 Seljord | Road Cuts with Contour Blasting","isPartOf":{"@id":"https:\/\/kjellfoss.no\/#website"},"primaryImageOfPage":{"@id":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#primaryimage"},"image":{"@id":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#primaryimage"},"thumbnailUrl":"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/08\/6.jpg-Seljord.jpg","datePublished":"2023-09-01T07:22:06+00:00","dateModified":"2025-11-05T11:30:53+00:00","description":"Contour blasting of 165,000 m\u00b3 of rock for road cuts on E134 \u00c5rhus \u2013 Seljord. Efficient and precise blasting solutions.","breadcrumb":{"@id":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#breadcrumb"},"inLanguage":"en-GB","potentialAction":[{"@type":"ReadAction","target":["https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/"]}]},{"@type":"ImageObject","inLanguage":"en-GB","@id":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#primaryimage","url":"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/08\/6.jpg-Seljord.jpg","contentUrl":"https:\/\/kjellfoss.no\/wp-content\/uploads\/2023\/08\/6.jpg-Seljord.jpg","width":1250,"height":960,"caption":"Ferdig veiskj\u00e6ring p\u00e5 E134 mellom \u00c5rhus og Seljord med 165 000 m\u00b3 kontursprengning p\u00e5 begge sider av skj\u00e6ringen."},{"@type":"BreadcrumbList","@id":"https:\/\/kjellfoss.no\/tidligere-prosjekter\/vei-og-jernbaneprosjekt\/e134-arhus-seljord\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Hjem","item":"https:\/\/kjellfoss.no\/"},{"@type":"ListItem","position":2,"name":"E134 \u00c5rhus &#8211; Seljord"}]},{"@type":"WebSite","@id":"https:\/\/kjellfoss.no\/#website","url":"https:\/\/kjellfoss.no\/","name":"Kjell Foss AS","description":"Fjellsprengning og fjellsikring i hele Norge","publisher":{"@id":"https:\/\/kjellfoss.no\/#organization"},"alternateName":"Kjell Foss AS","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/kjellfoss.no\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-GB"},{"@type":"Organization","@id":"https:\/\/kjellfoss.no\/#organization","name":"Kjell Foss AS","alternateName":"Kjell Foss AS","url":"https:\/\/kjellfoss.no\/","logo":{"@type":"ImageObject","inLanguage":"en-GB","@id":"https:\/\/kjellfoss.no\/#\/schema\/logo\/image\/","url":"https:\/\/kjellfoss.no\/wp-content\/uploads\/2025\/02\/kjell_foss_logo_horizontal_640px-1.png","contentUrl":"https:\/\/kjellfoss.no\/wp-content\/uploads\/2025\/02\/kjell_foss_logo_horizontal_640px-1.png","width":640,"height":140,"caption":"Kjell Foss AS"},"image":{"@id":"https:\/\/kjellfoss.no\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/kjellfoss.no\/","https:\/\/www.instagram.com\/kjellfoss_as\/","https:\/\/www.linkedin.com\/company\/kjell-foss-as\/"]},{"@type":"Person","@id":"https:\/\/kjellfoss.no\/#\/schema\/person\/1a569ead06f21069a291154e44c08ee9","name":"Ida Christine","image":{"@type":"ImageObject","inLanguage":"en-GB","@id":"https:\/\/kjellfoss.no\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/46bf5731d6e5f54c2b451c4f4c6756ccc3a79bfb90b2abd1e0bf3cea153cb2c8?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/46bf5731d6e5f54c2b451c4f4c6756ccc3a79bfb90b2abd1e0bf3cea153cb2c8?s=96&d=mm&r=g","caption":"Ida Christine"},"sameAs":["http:\/\/kjellfoss.hornstaging.no"],"url":"https:\/\/kjellfoss.no\/en\/author\/ida-christine\/"}]}},"_links":{"self":[{"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/posts\/9227","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/comments?post=9227"}],"version-history":[{"count":5,"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/posts\/9227\/revisions"}],"predecessor-version":[{"id":13220,"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/posts\/9227\/revisions\/13220"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/media\/9235"}],"wp:attachment":[{"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/media?parent=9227"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/categories?post=9227"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/kjellfoss.no\/en\/wp-json\/wp\/v2\/tags?post=9227"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}